• MAY - AUGUST 2024

    INITIAL NOTICES SENT
    General Information Notices (GIN) were delivered to inform tenants of the proposed project and their potential rights under federal relocation law.

  • OCTOBER - NOVEMBER 2024

    ELIGIBILITY NOTICES ISSUED
    Tenants who qualify for relocation assistance received formal Notices of Eligibility outlining their benefits and next steps.

  • LATE 2024

    90-DAY VACATE NOTICES BEGIN
    Households began receiving 90-day written notices advising of the date by which they would need to vacate, in accordance with federal requirements.

  • STARTING FEBRUARY 2025

    RESIDENT MOVES BEGIN
    Relocation of eligible households will begin in phases, based on housing availability and tenant readiness.

  • WITHIN 12 - 18 MONTHS

    RELOCATE ALL HOUSEHOLDS
    The relocation process is expected to be completed between early 2026 and mid-2026, with ongoing support available throughout.

  • NEXT?

    Updates to follow

Updated Waipouli Relocation Plan
The Courtyards at Waipouli Relocation Plan has been updated as of October 15, 2025. An earlier version of the plan dated November 11, 2024 was previously available on this site. Please refer to this most recent version for the latest information. For full context and specific details, see the complete