Option 1: Timeline Cards - Waipouli Relocation Timeline

Relocation Timeline by Building

Please Note: This schedule is subject to change. Unforeseen events or delays may impact the timeline. Updates will be posted if significant changes occur.

Click any building to view detailed timeline information

PHASE 1: Building 04 Urgent
8 units • 6 occupied, 2 vacant
Notice Date
Dec 15, 2025
Notice to Vacate
December 15, 2025
Must Vacate By
March 31, 2026
Construction Period
April 1 - May 31, 2026
DHHL Ready
June 1, 2026
Notice Period
106 days
Construction Duration
61 days
PHASE 2: Building 10
10 units • 6 occupied, 4 vacant
Notice Date
Jan 29, 2026
Notice to Vacate
January 29, 2026
Must Vacate By
May 31, 2026
Construction Period
June 1 - July 31, 2026
DHHL Ready
August 1, 2026
Notice Period
122 days
Construction Duration
61 days
PHASE 3: Building 01
8 units • 8 occupied
Notice Date
Mar 15, 2026
Notice to Vacate
March 15, 2026
Must Vacate By
July 31, 2026
Construction Period
Aug 1 - Sept 14, 2026
DHHL Ready
October 1, 2026
Notice Period
138 days
Construction Duration
45 days
PHASE 4: Building 05
8 units • 8 occupied
Notice Date
Apr 29, 2026
Notice to Vacate
April 29, 2026
Must Vacate By
September 14, 2026
Construction Period
Sept 15 - Oct 29, 2026
DHHL Ready
November 1, 2026
Notice Period
138 days
Construction Duration
45 days
PHASE 5: Building 09
8 units • 8 occupied
Notice Date
Jun 13, 2026
Notice to Vacate
June 13, 2026
Must Vacate By
October 29, 2026
Construction Period
Oct 30 - Dec 13, 2026
DHHL Ready
January 1, 2027
Notice Period
138 days
Construction Duration
45 days
PHASE 6: Building 03
8 units • 7 occupied, 1 vacant
Notice Date
Jul 28, 2026
Notice to Vacate
July 28, 2026
Must Vacate By
December 13, 2026
Construction Period
Dec 14, 2026 - Jan 27, 2027
DHHL Ready
February 1, 2027
Notice Period
138 days
Construction Duration
45 days
PHASE 7: Building 06
8 units • 8 occupied
Notice Date
Sep 11, 2026
Notice to Vacate
September 11, 2026
Must Vacate By
January 27, 2027
Construction Period
Jan 28 - Mar 13, 2027
DHHL Ready
April 1, 2027
Notice Period
138 days
Construction Duration
45 days
PHASE 8: Building 07
8 units • 7 occupied, 1 vacant
Notice Date
Oct 26, 2026
Notice to Vacate
October 26, 2026
Must Vacate By
March 13, 2027
Construction Period
Mar 14 - Apr 27, 2027
DHHL Ready
May 1, 2027
Notice Period
138 days
Construction Duration
45 days
PHASE 9: Building 08
8 units • 8 occupied
Notice Date
Dec 10, 2026
Notice to Vacate
December 10, 2026
Must Vacate By
April 27, 2027
Construction Period
Apr 28 - Jun 11, 2027
DHHL Ready
July 1, 2027
Notice Period
138 days
Construction Duration
45 days
PHASE 10: Building 02
8 units • 5 occupied, 3 vacant
Notice Date
Jan 24, 2027
Notice to Vacate
January 24, 2027
Must Vacate By
June 11, 2027
Construction Period
Jun 12 - Jul 26, 2027
DHHL Ready
August 1, 2027
Notice Period
138 days
Construction Duration
45 days

Updated Waipouli Relocation Plan: The Courtyards at Waipouli Relocation Plan has been updated as of October 15, 2025. An earlier version of the plan dated November 11, 2024 was previously available on this site. Please refer to this most recent version for the latest information. For full context and specific details, see the complete
Courtyards at Waipouli Relocation Plan.