Building 8 Key Steps

Step Date Days from Today (Dec 9, 2025)
90-Day Notice Issued November 26, 2026 352 days
Vacate By March 1, 2027 447 days
Construction Starts April 1, 2027 478 days
Construction Complete May 31, 2027 538 days
Relocation Timeline - Courtyards at Waipouli

Building 8 Relocation Timeline

Courtyards at Waipouli | Phase 9 of 10

📢 90-Day Notice
November 26, 2026
Official notification period begins - 90 days before required move date
📦 Vacate Date
March 1, 2027
All residents must vacate by this date - relocation assistance provided
🏗️ Construction Period
April 1 - May 31, 2027
Building renovation and improvement work - approximately 2 months
Project Complete
May 31, 2027
Construction finished - building ready for new occupancy
Timeline Key
Notice Period
Move Out
Construction
Completion

Building 8 residents will receive their 90-day notice in approximately 11.5 months (November 26, 2026).

Updated Waipouli Relocation Plan: The Courtyards at Waipouli Relocation Plan has been updated as of October 15, 2025. An earlier version of the plan dated November 11, 2024 was previously available on this site. Please refer to this most recent version for the latest information. For full context and specific details, see the complete
Courtyards at Waipouli Relocation Plan.